Nov 23 : Applied Digital said on Monday it has leased 150 megawatts of critical IT capacity to an investment-grade hyperscaler in a deal expected to generate $5.4 billion in contracted revenue over a base term of 18 years.
The deal follows another 15-year, 210 MW lease worth about $5.2 billion that the data center company signed in June at its Delta Forge 2 site.
• The lease with the tenant, which the company did not name, can be extended to a total of 33 years, with the deal worth about $12.7 billion if all renewal options are exercised
CNA Games
Guess Word
Crack the word, one row at a time
Buzzword
Create words using the given letters
Mini Sudoku
Tiny puzzle, mighty brain teaser
Mini Crossword
Small grid, big challenge
Word Search
Spot as many words as you can
Show More
Show Less
• Applied Digital said the lease carries improved commercial terms over its prior leases, including higher pricing
• The company said its total contracted base-term lease revenue now exceeds $41 billion, or about $100 billion with renewals
• About 75 per cent of contracted base-term lease revenue is now tied to investment-grade customers, the company added
• "We plan to finance this build through our established structure," CFO Saidal Mohmand said in a statement, citing the company's $5 billion equity partnership with Macquarie Asset Management, followed by project financing
• Delivery of the capacity is expected to begin in the first half of 2028, subject to development milestones, utility arrangements and regulatory approvals