Former Minister for Local Government and Rural Reorganisation, Martin Adjei-Mensah Korsah, has questioned the government’s progress on housing commitments, arguing that the 2027 Budget fails to adequately account for earlier targets and outstanding projects.
In an assessment of the 2027 Budget’s provisions for the Works, Housing and Water Resources sector, shared on Facebook on Wednesday, November 25, the former Minister said several housing commitments remained unreconciled, raising concerns about delivery timelines, funding and access to affordable homes.
He cited the Saglemi Housing Project, noting that the 2026 Budget had set a target of making 8,000 units habitable in 2026, while the 2027 Budget schedules 1,506 units for delivery in 2027, including 700 by March. He said the government had not explained the change in scope or accounted for the earlier target.
Mr Adjei-Mensah Korsah also pointed to the 800 housing units at Kpone, which remain reported at 80 per cent completion, despite an earlier ministerial statement in April indicating that the project was expected to be completed by September 2026.
He said revised timelines should not replace an account of previous commitments.
On rental and homeownership programmes, he said the previous year’s commitment to provide 10,000 additional rent-to-own beneficiaries had not been properly reconciled with the latest figures.
The 2027 Budget reports 917 rental-assistance beneficiaries as of September 2026 and 5,647 beneficiaries since the programme began, but these are different schemes and measures.
The former Minister further raised concerns about inconsistencies in the financing of the Housing Fund. He said paragraph 1557 of the Budget provides GH¢500 million, while Appendix 4A lists GH¢1 billion, with the latter matching a pledge made by the President in October.
He also questioned the new provision of approximately GH¢103 million for district housing, against the GH¢500 million earmarked for the programme in 2026, and called for a clear account of the funds and progress made.
Mr Adjei-Mensah Korsah argued that the government must move beyond announcing housing numbers and demonstrate how its programmes will make homes affordable.
He called for the publication of prices, deposits, financing terms and monthly payment limits, alongside delivery targets for different income groups.
He said the government should also publish a funded completion and handover plan prioritising viable housing projects nearing completion, while ensuring that informal-sector workers are assessed through verifiable income, cash flow and savings arrangements.