By noon on Saturday, the nearly 10 km section between Long Thanh Bridge and the National Highway 51 interchange in Dong Nai had been largely widened to 10 lanes. From midnight on Sunday, traffic is scheduled to move onto the new lanes so the existing road surface can be upgraded.
The expansion project began in August 2025 with total investment of more than VND14.945 trillion (US$580 million). It covers about 22 km, from the Ring Road 2 interchange in Ho Chi Minh City to the Bien Hoa-Vung Tau Expressway in Dong Nai.
Once complete, it will strengthen the link between Ho Chi Minh City and Long Thanh International Airport, Vietnam's largest airport by area, which is expected to begin operations in December.
At the National Highway 51 interchange, the ramp onto the expressway has been completed. The deck of an overpass about 300 m long is also finished and will be asphalted soon.
The interchange links the expressway with National Highway 51, helping connect Long Thanh airport to the road network of southeastern Vietnam.
Between the National Highway 51 toll station and the Provincial Road 769 interchange, the widened branches have been completed and connected to the existing expressway.
Road signs, direction signs, medians, embankment slopes and lighting were completed ahead of the opening. Drivers are advised to watch carefully and follow road signs and instructions from traffic controllers.
Contractors are finishing the last items, including lane markings, slope reinforcement and road cleaning, to ensure safe conditions for traffic.
Contractors are finishing the last items, including lane markings, slope reinforcement and road cleaning, to ensure safe conditions for traffic.
Contractors are finishing the last items, including lane markings, slope reinforcement and road cleaning, to ensure safe conditions for traffic.
From Sunday, vehicles will be diverted onto the new lanes so contractors can renovate and upgrade the existing road surface, which sits about 10 cm lower than the widened section.
Opening the widened section early gives contractors room to work on the existing lanes and to store materials and machinery, speeding up construction.
After more than a year of construction, the expansion project is about 81% complete, and work is being accelerated so it can be largely finished in 2026.
A new parallel span of Long Thanh Bridge, more than 2 km long and nearly 24 m wide with five lanes, is being built to the right of the existing bridge in the Ho Chi Minh City-Dong Nai direction. The project's largest and most complex item, it is expected to be finished in the first quarter of 2027.
After more than a year of construction, the expansion project is about 81% complete, and work is being accelerated so it can be largely finished in 2026.
A new parallel span of Long Thanh Bridge, more than 2 km long and nearly 24 m wide with five lanes, is being built to the right of the existing bridge in the Ho Chi Minh City-Dong Nai direction. The project's largest and most complex item, it is expected to be finished in the first quarter of 2027.
After more than a year of construction, the expansion project is about 81% complete, and work is being accelerated so it can be largely finished in 2026.
A new parallel span of Long Thanh Bridge, more than 2 km long and nearly 24 m wide with five lanes, is being built to the right of the existing bridge in the Ho Chi Minh City-Dong Nai direction. The project's largest and most complex item, it is expected to be finished in the first quarter of 2027.
Expansion of the Ho Chi Minh City-Long Thanh Expressway. Video by VnExpress/Quynh Tran
The 55 km Ho Chi Minh City-Long Thanh-Dau Giay Expressway, connecting Ho Chi Minh City with Dong Nai, opened in 2015 at a total investment of VND20.6 trillion ($800 million). After more than 10 years in operation, it is frequently congested because of heavy traffic, especially on weekends and public holidays.